|
|
Everlast Pavements |
|
|
Asphalt concrete pavement in service
today can be called "neverlast". These
pavements never last more than a few years after
construction before the first signs of distress can
be observed. "Neverlast" pavements are constructed
of conventional asphaltic concrete and that also includes
"superpave". Very few conventional pavements
last more than 10 years and have to be re-surfaced or
reconstructed. This routine is repeated endlessly and
without hope of ever getting more service life out of the
pavement. This means that towns, cities, counties,
states and provinces spend enormous amounts of money only to
have pavements fail repeatedly. "Everlast"
pavements on the other hand greatly mitigate or completely
eliminate most failures for several decades. Numerous
"Everlast" pavements have been constructed in the
past 20 years. They have been shown to require very
minor maintenance or no maintenance at all. What is an
"Everlast" pavement and how does it differ from
the "neverlast" conventional pavements? |
/tr>
|
|
| 1. |
"Everlast"
pavements consist of composite construction.
The two lift system has a bottom lift which can be
placed direct over a gravel base or placed directly
over the old failed pavement. This is followed
by placing a lift of conventional asphalt concrete
over the bottom lift which makes this pavement
"everlasting". The "Everlast"
bottom lift is composed of a processed, washed and
non-crushed aggregate and a special chemically
modified asphalt cement. The conventional top
lift can be a dense-graded or gap-graded asphalt
concrete such as "superpave". An
essential criteria for the conventional gap is that
the amount of -200 material is not to exceed 5.5
percent. This will ensure that the asphalt
film thickness around the particles is greater than
8.0 microns. When this is so, the top lift
will resist raveling and premature oxidation of the
asphalt cement binder. The "Everlast"
bottom lift will be rich in asphalt and will have an
asphalt film thickness of 20 to 23 microns. |
|
|
| 2. |
The
"Everlast" bottom asphalt concrete mix is
mixed between 250oF and 270oF
in a drum or batch mixing plant. Because of
the chemically modified asphalt binder and the low
mixing temperature, the mix produced does not emit
any noticeable smoke or any noticeable odour as a
result. This mix has a lower impact on the
environment and on the health of the paving crews. |
|
|
| 3. |
"Everlast"
Pavements (Analysis Of Performance)
The "Everlast" pavements have been in
service for 20 years. During this time it was
observed that these pavements are superior in every
way to conventional asphalt concrete
pavements. An analysis of their performance is
as follows: |
|
|
|
| 1. |
Lower
Impact On The Environment
The "Everlast" bottom mix is
produced at a lower temperature than
conventional mix. As a result, very
little smoke or odour is evident. |
|
|
| 2. |
Lower
Impact On The Health Of Paving Crews
Because of the low smoke and low odour
levels during production and placing of the
"Everlast" asphalt concrete bottom
mix, the health of the paving crews is
impacted less. |
|
|
| 3. |
Placing
Of The "Everlast" Bottom Mix
The "Everlast" bottom mix can be
placed directly on a properly constructed
gravel base in the case of new
construction. When rehabilitating an
old failed pavement, the "Everlast"
bottom mix can be placed on the old pavement
without prior repair of the old failed
pavement. A prior tackcoat is also not
required. The placing temperature can
be as low as 200oF without
adverse impact on the density of the
compacted mix. |
|
|
| 4. |
Compaction
Of "Everlast" Bottom Mix
The "Everlast" bottom mix can be
readily compacted to its maximum density
with only minimal effort. To compact
the mix requires one large dual steel drum
roller of 5 to 7 tonne capacity and a small
dual steel drum roller. The compacted
"Everlast" bottom mix (minimum 1 1/2
inches) for rehabilitating an old
failed pavement or (minimum 2 inches) for
new construction will be rolled to a table
top smoothness. |
|
|
| 5. |
Capping
Of The "Everlast" Bottom Lift
Capping of the "Everlast" bottom
lift is done with conventional dense-graded
asphalt concrete or with gap-graded (superpave)
asphalt concrete mix. The conventional
asphalt concrete mix must have a -200
content of no more than 5.0 percent and must
be compacted to 93 percent of theoretical
maximum density. The resultant "Everlast"
pavement will be as smooth as a table top
thanks to the "Everlast" bottom
lift. Due to the high asphalt film
thickness of 20 to 23 microns around the
particles of the "Everlast" bottom
mix and the porous surface of it, a
tenacious bond is formed. This bond is
highly unlikely to ever break. As a
result, no debonding of the "Everlast"
bottom lift and conventional cap will take
place. |
|
|
|
|
|
Characteristic Performance Of The "Everlast"
Pavement
|
|
|
| 1. |
Reflective
Cracking And Potholing
It has been observed that
reflective cracking, potholing and other problems have
been drastically mitigated or completely eliminated
after 20 years in service. |
|
|
| 2. |
Delamination Of Successive Lifts
This has also not ocurred after a
service life of 20 years. As a result, no
potholes due to lift delamination have been observed
after 20 years in service.
|
|
|
| 3. |
Longitudinal Cracking Of Cold Joint
Cracking of the longitudinal (cold)
joint has not been observed in any of the "Everlast"
pavements. The total number of "Everlast"
pavements in service are about forty (40).
When a construction joint cracks, it becomes wider
and wider resulting in potholes along this joint as
in conventional construction. This problem is
totally eliminated with "Everlast"
pavements.
|
|
|
| 4. |
Rutting Of The "Everlast"
Pavements
All of the "Everlast"
pavements constructed in the last 20 years have not
rutted. Some carry exceedingly heavy loads such
as large gravel trucks, concrete mixing trucks as
well as large transport trucks. The number of
these per day is in the hundreds. It has been
observed that even in intersections where the trucks
come to a stop, no rutting has been observed. The "Everlast"
pavements will totally mitigate rutting and
washboarding. |
|
|
| 5. |
Effect Of Freezing And Thawing
When moisture enters the
open-graded structure of the "Everlast"
bottom lift, it will expand into the open
and inter-connected voids upon freezing. As a
result, there is no internal stress on the pavement
that could result in cracking. It has also been
observed that thermal cracking (transverse cracks)
have also been drastically mitigated over
conventional pavements. |
|
|
|
|
With the development of the "Everlast" pavement we
have found the holy grail of asphalt paving
technology. No future paving system will equal or
supercede the "Everlast" pavement system.
It has been a long journey since Professor E.J. DeSmedt,
a Belgian chemist, constructed the first ever asphalt
pavement in Newark, New Jersey in 1870. Since then,
great progress has been made to produce better and better
asphalt concrete paving mix. Today we have
sophisticated and highly computerized mixing plants, complex
and high-production paving machines and rollers, and page
after page of specifications. However, what we do not
have is maintenance-free pavements to go along with today's
technology. Along this journey we have had a few
thinkers. But mostly it was the blind leading the
blind. Along the way, we have come upon many forests
but we did not see them because we were too busy counting
the trees.
I, Peter Sontowski, stand before the gates to the holy
grail of asphalt paving technology. Follow me and you
will have "Everlasting Pavements". "Let
me open the gates for you!"
|
|
|
|
|
|